SPX

SPX had purchased a new piece of equipment which required a new concrete slab inside their facility with very detailed specifications. Repair technicians at CCS used great care to remove existing sections of concrete where the equipment was to be located. These locations were excavated and prepped with a new rock base and rebar structure as per the design. We then installed a 12″ thick concrete slab over a 12″ compacted base with a flat and level surface within a 1/4″ over the entire area to ensure a flat surface for equipment mounts. All processes were performed while SPX was operating at full capacity with little impact on their daily activities. Dust levels were kept at a minimum to ensure a safe work environment for SPX as well as CCS employees. This project was completed in just 2 days.